Aligned Data Centers IAD-04 Frederick

Aligned Data Centers

Under constructionMixed-useConfirmed

Key facts

Location
MD, Frederick County
Capacity
72 MW planned
Powered by
Announced
2025-02
Last updated

Civic impact

Economics

Land
75 acres

Energy & water

Energy source
Grid · Utility: Potomac Edison / FirstEnergy
Cooling
Hybrid

Utility-served (FirstEnergy / Potomac Edison, multi-gigawatt scale per Frederick Chamber). Aligned commits to "100% renewable power" (procurement, not dedicated generation). 172 emergency diesel generators (508 MW combined) MDE-approved (Jan 2025) for backup only.

Aligned describes "Delta³ air cooling arrays" plus "DeltaFlow liquid cooling" within a "closed-loop chilled water system" and markets "near-zero water consumption"; no facility MGD disclosed. Cooling spec is campus-level and may not be IAD-04-specific.

Public subsidies

  • Maryland Data Center Sales & Use Tax Exemption — 10-year exemption on qualified data-center personal property (extendable to 20 years for $250M+ investment). Aligned's CEO cited "attractive tax exemptions" for choosing Frederick; statutory eligibility only, no project-specific certification confirmed.
    Maryland · 2020

Community sentiment

Opposed

Frederick County Data Center Referendum Committee collected 21,000+ signatures opposing overlay zone expansion. Maryland Supreme Court scheduled to hear referendum appeal. Frederick County Council created Critical Digital Infrastructure Overlay Zone in January 2026.

What Now for Quantum Loophole and the Quantum Frederick Data Center Campus?

Status history

  1. Proposed

    Aligned announced campus at Quantum Frederick; Maryland regulations on backup generators initially delayed groundbreaking

    Aligned breaks ground on 72MW Maryland data center in Quantum Frederick Park
  2. Under construction

    Groundbreaking February 5, 2025 after Maryland amended generator regulations. 450,000 sq ft, two-story facility; Turner Construction GC. Structural topping-out milestone completed.

    Aligned breaks ground on 72MW Maryland data center in Quantum Frederick Park

Location

Sources & data provenance

Confirmed: data verified against official filings, permits, or direct operator announcements.

Last updated: