Gilroy, CA · Santa Clara County · 36.997°N 121.541°W

Amazon AWS Gilroy Data Center

Amazon Web Services

Under constructionMixed-useConfirmed

Key facts

Location
Gilroy, CA, Santa Clara County
Capacity
98 MW planned
Powered by
Announced
2025-07
Last updated

Civic impact

Economics

Investment
$2B
Land
56 acres

Energy & water

Energy source
Grid · Utility: Pacific Gas & Electric (PG&E)
Cooling
Hybrid
Water use
0.016 MGD

Phase 1: 49MW PG&E grid connection. Potential 50MW Battery Energy Storage System (BESS) on-site. Phase 2 adds a second 218,000 sq ft building with alternative backup power solutions. Total planned capacity ~98MW across both phases.

Final EIR-certified use is 23 acre-feet/year total (~7.49 million gallons/yr) at full build-out — 18 AFY for cooling (~0.016 MGD), 3 AFY landscaping, 2 AFY domestic (FEIR p.186); drawn from Gilroy potable supply pending a recycled-water pipeline. Evaporative cooling is triggered only when outdoor temperature exceeds 83F (~3% of the year). Amazon's promotional figure of ~4 million gallons/yr (~36 households) is roughly half the FEIR-certified total and is disputed in a CEQA challenge; Amazon says it aims for 100% reclaimed cooling water by 2030.

Community sentiment

Contested

Organized resident opposition active. Concerns cited: utility cost spikes, noise, fire and explosion risk from large-scale lithium BESS, and objection to AI use. An appeal was filed July 21, 2025, subsequently withdrawn August 18, 2025. Opponents requested Amazon guarantee the facility would not be used exclusively for AI workloads.

Amazon Data Services Gains Approval for Data Center on 56 Acres in Gilroy, California

Status history

  1. Proposed

    Permit application initially received by City of Gilroy; Amazon purchased 56-acre site for $31.3M in 2020

    Amazon Data Services Gains Approval for Data Center on 56 Acres in Gilroy, California
  2. Permitted

    Gilroy Community Development Director Sharon Goei approved Phase 1 (218,000 sq ft building, 49MW PG&E connection) on July 3, 2025; appeal filed July 21, 2025, withdrawn August 18, 2025

    Gilroy Data Center (by Amazon Web Services) — Official City Project Page
  3. Under construction

    Grading permit issued December 11, 2025; building permit issued March 19, 2026; City of Gilroy project listing shows status as Under Construction

    Gilroy Data Center (by Amazon Web Services) — Official City Project Page

Location

Sources & data provenance

Confirmed: data verified against official filings, permits, or direct operator announcements.