Toronto, SD · Deuel County · 44.567°N 96.620°W
Applied Digital Deuel County AI Campus
Applied Digital Corporation
Key facts
- Location
- Toronto, SD, Deuel County
- Capacity
- 430 MW planned
- Powered by
- —
- Announced
- 2025
- Last updated
Civic impact
Energy & water
- Energy source
- Grid · Utility: Otter Tail Power
Proposed site was near Otter Tail Power transmission lines and a natural gas plant in Astoria.
Status history
- Proposed
Applied Digital proposed a 430 MW AI data center campus near Toronto, SD, with up to $16 billion of announced investment and up to 200 permanent jobs. Data Center Dynamics reported the company was 'proposing an AI data center development east of Toronto in South Dakota.'
Applied Digital proposes multi-billion-dollar data center in South Dakota - Cancelled
Applied Digital told Keloland (statement March 2026) that the project was 'unlikely to go forward,' citing the South Dakota legislature's failure to pass a 50-year sales-tax exemption on IT equipment, and said it would let its land option near Toronto lapse.
Applied Digital says data center near Toronto, South Dakota, unlikely to go forward
Location
Sources & data provenance
Confirmed: data verified against official filings, permits, or direct operator announcements.
Last updated:
- Data Center DynamicsRetrieved:
- Data Center DynamicsRetrieved:
Compute Atlas is community-correctable. If you have better data, please open an issue.
Suggest a correction →