Massillon, OH · Stark County · 40.775°N 81.535°W
Bitdeer Massillon Facility
Bitdeer
Key facts
- Location
- Massillon, OH, Stark County
- Capacity
- 221 MW planned
- Powered by
- —
- Announced
- —
- Last updated
Civic impact
Economics
- Investment
- $100M
- Land
- 31 acres
- Jobs
- 70 permanent
Mining
- Hardware
- ASIC
- Power arrangement
- unknown
Community sentiment
Local opposition petition ("BitDeer Bitmine in Massillon" nuisance petition) circulated via MoveOn; a Massillon city council vote reportedly allowed the project to proceed, though the source for that vote could not be independently fetched/verified this session.
Petition in Opposition to BitDeer Bitmine in MassillonStatus history
- Proposed
Bitdeer purchases a 31-acre parcel.
What's it like inside Bitdeer's crypto mining operation in Massillon? - Under construction
First miners begin operating; a fire the same month damages 2 of the ~24-26 planned buildings (~26MW), with re-energization of those buildings targeted for end of September 2026. Remainder phased toward full 221MW through 2026.
What's it like inside Bitdeer's crypto mining operation in Massillon?
Location
Sources & data provenance
Confirmed: data verified against official filings, permits, or direct operator announcements.
Last updated:
- Yahoo FinanceRetrieved:
- AOLRetrieved:
- BaxtelRetrieved:
- MoveOnRetrieved:
Compute Atlas is meant to be corrected. If you have better data on this facility, please open an issue.
Suggest a correction →