Mesa, AZ · Maricopa County · 33.376°N 111.620°W
Google Redhawk Mesa Data Center Campus
Key facts
- Location
- Mesa, AZ, Maricopa County
- Capacity
- 400 MW planned
- Powered by
- 400MW solar and wind (Salt River Project)
- Announced
- 2019-01
- Last updated
Civic impact
Economics
- Investment
- $1B
- Land
- 187 acres
Energy & water
- Energy source
- Solar · Utility: Salt River Project (SRP)
- Cooling
- Air-cooled
400MW from in-state solar and wind farms committed for Phase 2 buildout
Google built the Mesa campus as air-cooled, chosen for Arizona's watershed scarcity; Mesa's economic-development director described it at groundbreaking as a 'cutting-edge, air-cooled data center campus.' The 2019 City of Mesa development agreement separately provided for the city to supply up to ~1 million gallons/day at launch, scaling toward ~4 million gallons/day at full build-out — a contractual water allocation/backup (on-site storage, existing wells, acquired water rights, long-term storage credits), not confirmed operational cooling consumption. No operational water-use figure has been published.
Public subsidies
- Government Property Lease Excise Tax (GPLET) — approx. $16M property-tax reduction over 25 yearsCity of Mesa, AZ · 2019
Community sentiment
Mesa City Council approved the $1B development and GPLET agreement in July 2019 (Mayor John Giles called it 'a home run'); one councilmember abstained as a Google shareholder and voiced reservations about large-corporation tax breaks. The city projected net positive tax revenue.
Mesa Council approves $1bn Google data center, with $16m in tax breaksStatus history
- Proposed
Google filed plans as 'Stone Applications LLC' for 187 acres at NW corner of Elliot and Sossaman roads
- Operational
Phase 1 (288,530 sq ft data hall, Redhawk 1) went operational July 2025 for core cloud and AI services
Google breaks ground on Mesa data center campus in Arizona - Under construction
Phase 2 (280,000 sq ft, 185 acres) under construction targeting 2027; Phase 3 (283,500 sq ft) under Mesa Design Review Board review
Google Planning Next Phase of Mesa Data Center Facility
Location
Sources & data provenance
Confirmed: data verified against official filings, permits, or direct operator announcements.
Last updated:
- Data Center DynamicsRetrieved:
- AZBEXRetrieved:
- Data Center DynamicsRetrieved:
Compute Atlas is community-correctable. If you have better data, please open an issue.
Suggest a correction →