El Paso, TX · El Paso County · 31.810°N 106.550°W

Meta El Paso AI Data Center Campus

Meta

Under constructionAI-specificConfirmed

Key facts

Location
El Paso, TX, El Paso County
Capacity
1,000 MW planned
Powered by
Grid (El Paso Electric, renewable-matched); 366 MW McCloud gas plant proposed
Announced
2025-10
Last updated

Civic impact

Economics

Investment
$10B
Land
1,000 acres
Jobs
4,000 construction · 300 permanent

Energy & water

Energy source
Mixed · Utility: El Paso Electric
Cooling
Closed-loop

Meta claims 100% renewable energy matching via Texas clean energy contracts (5,000+ MW contracted statewide). El Paso Electric separately seeking PUCT approval for a 366 MW natural gas McCloud facility to power this campus, which drew environmental opposition.

Zero operational water use for most of the year via closed-loop liquid cooling. Commitment to restore 200% of consumed water to local watersheds by 2030.

Community sentiment

Contested

Sembrando Esperanza Coalition and environmental groups oppose the proposed natural gas plant, citing air quality and rate equity concerns. Meta committed $500,000 to workforce development via El Paso Public Schools.

Plan to run El Paso data center on natural gas sparks concern

Status history

  1. Proposed

    Meta announces El Paso campus with initial $1.5B investment.

    Meta breaks ground on El Paso AI-optimized data center
  2. Under construction

    Groundbreaking October 15, 2025. Site is Meta's 29th data center globally, third in Texas.

    Meta breaks ground on El Paso AI-optimized data center

Location

Sources & data provenance

Confirmed: data verified against official filings, permits, or direct operator announcements.

Last updated:

Compute Atlas is community-correctable. If you have better data, please open an issue.

Suggest a correction →