Malaga, WA · Chelan County · 47.230°N 120.200°W

Microsoft Malaga Campus

Microsoft

Under constructionAI-specificConfirmed

Key facts

Location
Malaga, WA, Chelan County
Capacity
288 MW planned
Powered by
Chelan County PUD hydropower (carbon-free)
Announced
2023-03
Last updated

Civic impact

Economics

Land
102.5 acres

Energy & water

Energy source
Hydro · Utility: Chelan County PUD
Cooling
Air-cooled

Carbon-free hydropower from Chelan PUD; 18 MW surplus hydropower through end of 2025, then long-term arrangement under utility energy marketing strategy. Under the June 2025 large-load contract, Microsoft will import new clean power from a third-party supplier for 2026-2040 (source undetermined); Chelan PUD is not obligated to serve its own hydropower. Microsoft funded the $86.5M Jumpoff Ridge substation.

Newest AI datacenter buildings designed for no evaporative cooling water use per Microsoft Community-First blog. Earlier permit data shows ~83 gpm per building for fire suppression and employee use, not cooling.

Community sentiment

Mixed

Chelan County PUD commissioners approved Microsoft's large-load power contract on June 16, 2025 (the first under the PUD's new large-load framework), structured so Microsoft bears the full cost and risk of its demand. Public comments centered on preserving reliability and affordable rates for existing customers, with some concern about service priority during energy shortfalls. No litigation.

PUD commissioners approve power contract for Microsoft data center

Status history

  1. Proposed

    Microsoft acquired 102.5 acres on Malaga Alcoa Highway for $9.2M across three parcels

    Microsoft Plans Three Data Centers in Malaga, Washington
  2. Permitted

    Permits filed for three data center buildings on Malaga Alcoa Highway; Chelan County

    Microsoft Plans Three Data Centers in Malaga, Washington
  3. Under construction

    Construction of first datacenter building commenced June 2023 per Microsoft Local blog; Jumpoff Ridge Substation also under construction on campus

    Malaga Datacenter Project Overview

Location

Sources & data provenance

Confirmed: data verified against official filings, permits, or direct operator announcements.

Last updated:

Compute Atlas is community-correctable. If you have better data, please open an issue.