← Back to the map
Pecos, TX · Reeves County · 31.420°N 103.490°W
Microsoft Pecos Data Center Campus
Microsoft
ProposedAI-specificConfirmed
Key facts
- Location
- Pecos, TX, Reeves County
- Capacity
- 2,000 MW planned
- Powered by
- Behind-the-meter natural gas plant (Chevron/Energy Forge One, up to 2.67 GW; GE Vernova turbines)
- Announced
- 2026-06
- Last updated
Civic impact
Economics
- Land
- 7,000 acres
- Jobs
- 6,000 construction
Energy & water
- Energy source
- On-site gas · Utility: Chevron/Energy Forge One LLC
- On-site generation
- 2,670 MW
- Cooling
- Closed-loop
20-year PPA with Energy Forge One (Chevron subsidiary) for dedicated behind-the-meter natural gas plant (~$7B plant cost). GE Vernova and Caterpillar/Solar Turbines. Campus designed to eventually integrate with ERCOT regional grid.
Closed-loop cooling designed to minimize water use, compared by Microsoft to a fast-food restaurant on a lifecycle basis.
Status history
- Proposed
Microsoft announces 2 GW campus in Pecos as one of largest single capacity additions in company history. Five-to-seven-year build-out planned.
Microsoft announces Pecos data center campus
Location
Sources & data provenance
Confirmed: data verified against official filings, permits, or direct operator announcements.
Last updated:
- MicrosoftRetrieved:
- Data Center DynamicsRetrieved:
Compute Atlas is community-correctable. If you have better data, please open an issue.