Spotsylvania, VA · Spotsylvania County County · 38.170°N 77.660°W

PowerHouse 95

PowerHouse Data Centers (American Real Estate Partners / AREP, joint venture with Harrison Street)

Under constructionLikely AI-specificReported

Key facts

Location
Spotsylvania, VA, Spotsylvania County County
Capacity
800 MW planned
Powered by
Announced
2024
Last updated

Civic impact

Economics

Land
145 acres

Energy & water

Energy source
Grid
Cooling
Unknown

Utility inferred from geographic service area and Dominion's Tributary 230 kV transmission project (SCC Final Order June 30, 2024) built specifically to serve Spotsylvania County data center demand. PH95-specific press materials do not name the utility. Rappahannock Electric Cooperative also serves parts of Spotsylvania County and cannot be ruled out.

Press materials do not disclose cooling approach for PH 95 specifically. PowerHouse has deployed direct-to-chip and closed-loop cooling at other campuses; no water draw figures available.

Community sentiment

Mixed

Spotsylvania County has experienced significant data center controversy: the board voted 4-3 in December 2025 to approve design standards; required special use permits for data centers in February 2026 (mirroring Loudoun, Prince William, and Henrico); public comments cited noise, grid strain, water supply risk, and visual impact. One project (Hunters Ridge South, 2.2M sq ft) passed 5-2 in August 2025. PowerHouse 95 itself was not identified as the specific target of organized opposition in sourced materials — it appears to have proceeded under earlier by-right industrial zoning rules. Rappahannock Electric Cooperative CEO told Spotsylvania officials that one data center can require as much energy as REC's entire customer base during peak demand.

Spotsylvania Board of Supervisors approves data center design standards

Status history

  1. Proposed

    PowerHouse announced completed purchase of 145 acres in Spotsylvania County along I-95/Hwy 17 corridor for PowerHouse 95 campus; three 300 MW substations planned.

    PowerHouse Data Centers announces purchase of 145 acres in Spotsylvania, VA for PowerHouse 95 campus
  2. Under construction

    Groundbreaking announced; company posted on LinkedIn 'Construction on PH 95 North is underway!' DCD coverage July 19, 2024.

    PowerHouse breaks ground on 800MW data center campus in Spotsylvania County, Virginia

Location

Sources & data provenance

Reported: data based on credible news outlets or industry sources.

Last updated:

Compute Atlas is community-correctable. If you have better data, please open an issue.

Suggest a correction →