← Back to the map
Palmetto, GA · Fulton County · 33.548°N 84.724°W
T5 @ Atlanta IV
T5 Data Centers
ProposedLikely AI-specificReported
Key facts
- Location
- Palmetto, GA, Fulton County
- Capacity
- 300 MW planned
- Powered by
- —
- Announced
- 2024-08-28
- Last updated
Civic impact
Economics
- Land
- 91 acres
Energy & water
- Energy source
- Grid
- Cooling
- Hybrid
On-site electrical substation providing grid power; substation expected operational 2026.
Air and liquid cooling designed for high-density AI workloads.
Community sentiment
Unknown
Status history
- Proposed
Land acquisition finalized; 91-acre site already zoned for data-center use; use permit still required
T5 Finalizes Land Acquisition in Atlanta to Support a 300 MW Data Center Campus - Proposed
T5 refiled modified plans: 1.32M sq ft, 3 buildings, up to 300 MW; the original June 2024 filing (495K sq ft, 2 buildings) was withdrawn
T5 files to develop data center campus outside Atlanta, Georgia
Location
Sources & data provenance
Reported: data based on credible news outlets or industry sources.
Last updated:
- Data Center DynamicsRetrieved:
- T5 Data CentersRetrieved:
- PR NewswireRetrieved:
- BisnowRetrieved:
- Atlanta Journal-ConstitutionRetrieved:
Compute Atlas is community-correctable. If you have better data, please open an issue.