Vantage Data Centers VA4 Stafford Campus

Vantage Data Centers

Under constructionMixed-useConfirmed

Key facts

Location
VA, Stafford County
Capacity
192 MW planned
Powered by
Announced
2025-11
Last updated

Civic impact

Economics

Investment
$2B
Land
82 acres
Jobs
1,100 construction · 50 permanent

Energy & water

Energy source
Grid · Utility: Dominion Energy
Cooling
Closed-loop

Closed-loop chilled water system with liquid-to-liquid cooling; LEED Silver target; designed to minimize water consumption

Status history

  1. Proposed

    Announced November 6, 2025; DPR Construction engaged as general contractor; three data centers, 929,000 sq ft total; first building target late 2027

    Vantage Data Centers Invests $2B in Fredericksburg Virginia Region
  2. Under construction

    Groundbreaking ceremony held November 6, 2025 per Vantage press release; active development underway with DPR Construction as general contractor.

    Vantage Data Centers Invests $2B in Fredericksburg Virginia Region

Location

Sources & data provenance

Confirmed: data verified against official filings, permits, or direct operator announcements.

Last updated:

Compute Atlas is community-correctable. If you have better data, please open an issue.