Chickasha, OK · Grady County · 35.053°N 97.936°W
Supplies power to Co-located data center at Chickasha Airport Industrial ParkCompany-level / grid-region purchase — no single named campus.
Phased build: 125-150 MW added roughly every six months, first phase 18-24 months, remaining phases over ~2.5 further years. Combined power-plant-plus-data-center investment reported at $3.5 billion or more; 280 acres purchased for $1.358 million, of which about 200 acres is designated for the power plant and data center and 80 acres for a commercial/industrial subdivision.
Natural gas supplied via an Energy Transfer connection; built under Oklahoma's SB 480 'behind the meter' law to serve a co-located data center rather than the grid.
Announced by developer Chet Hitt with Citizen Capital (financing, led by Bond Payne) and Lightfield Energy (plant construction, led by Billy Sorenson).
More details about the proposed Chickasha data centerReported: data based on credible news outlets or industry sources.