Community friction
Where the buildout meets resistance
Tracked sites with documented local friction — lawsuits, moratoria, referendums, and formal opposition. This is not a claim about the buildout as a whole; it is the sourced subset facing pushback, and every entry links to a source-cited record.
§ By reception
By reception
§ The sites
The sites
In litigation · 21
- Joliet Technology CenterPermittedHW Technology Park (Hillwood Investment Properties / PowerHouse Data Centers) · Joliet, IL
Hundreds of residents filled council chambers and overflow rooms; concerns over water/electricity consumption, noise pollution, and proximity to residential areas. Post-approval lawsuit filed naming City of Joliet, PowerHouse, and Hillwood as defendants.
- Project Cardinal Data Center CampusPermittedPioneer Development LLC · Yorkville, IL
Two active lawsuits as of July 2026. (1) John Bryan (filed Oct 28, 2025): a conditional settlement was before the June 23, 2026 City Council — terms limited to a phasing-order revision (NE-SE-W instead of NE-W-SE), no monetary payment to Bryan. (2) Preserve Our Yorkville & Community LLC (filed April 2026): broader suit alleging inadequate annexation/rezoning notice and deviation from the 2016 Comprehensive Plan; still ongoing as of June 30, 2026. Pioneer Development also sought an 18-month extension (to Dec 31, 2027) to close on all parcels — failure voids the annexation agreement. A $51M developer impact-fee package flows FROM the developer TO the city (schools/fire/projects), not a subsidy; no DCEO certification found and Illinois paused its Data Center Investment Program on July 1, 2026.
- Stargate The Barn CampusUnder constructionOpenAI / Oracle / Related Digital · Saline Township, MI
The Saline Township board voted 4-1 to deny the rezoning (Sept 2025); Related Digital sued two days later and a court-approved settlement allowed construction to proceed with ~$14M in community benefits. A resident later filed an Open Meetings Act challenge. At least 19 Michigan municipalities enacted data-center moratoriums afterward.
- Project AquilaProposedRCM Hill, LLC · TX
Hill County's 1-year moratorium (passed 3-2, May 12, 2026) was rescinded June 4, 2026 after RCM Hill filed a $100M federal lawsuit, which remains active seeking damages.
- Google Project Spade CampusUnder constructionGoogle · New Florence, MO
County commissioners unanimously approved; opposition group Preserve Montgomery County filed a Missouri Sunshine Law lawsuit against the commissioners (Feb 2026).
- Nebius AI Factory (Independence)Under constructionNebius Group · Independence, MO
Opponents raised concerns about water usage, electricity rate impacts, and wildlife habitat; filed lawsuit seeking a city-wide vote on the project; judge dismissed the lawsuit; city council approved bonds over public objections. Groundbreaking proceeded May 13, 2026.
- Project Washington (Starwood Digital Ventures)ProposedStarwood Digital Ventures · Delaware City, DE
DNREC Secretary denied Coastal Zone Act permit February 4, 2026 citing 516 backup diesel generators and 2.5 million gallons of stored diesel as unprecedented heavy industrial use under Delaware's 1971 Coastal Zone Act. Starwood appealed to Coastal Zone Industrial Control Board; hearing held March 24-26, 2026. Board UNANIMOUSLY UPHELD the denial March 26, 2026. Starwood expected to appeal to Delaware Superior Court and potentially Delaware Supreme Court; full resolution estimated 18 months to three years. First major CZA denial for a project of this scale in Delaware history. New Castle County legislators exploring new data center zoning category.
- Project Sail – Prologis Data Center CampusPermittedPrologis · Newnan, GA
Coweta County residents filed appeal in Coweta County Superior Court May 5, 2026 to reverse 3-2 rezoning vote. Separate eminent domain controversy: Georgia Power acquired easements on 330+ private properties for high-voltage transmission lines needed to serve new data centers.
- Bitdeer Clarington HPC/AI CampusUnder constructionBitdeer · Clarington, OH
American Heavy Plate Solutions LLC (a neighboring tenant leasing 9.9 of the 100-acre Hannibal Industrial Park) sued Bitdeer subsidiaries (Erie Creek LLC, Whitetail Creek LLC, Bitdeer Inc.) and the Monroe County Port Authority in the Court of Common Pleas of Monroe County, OH (disclosed in Bitdeer's SEC Form 6-K, Feb 2 2026), seeking declaratory and injunctive relief over a restrictive covenant in AHP's 2018 lease; Bitdeer says it will 'vigorously defend' and that construction/power timing 'may be affected.'
- Imperial Valley Computer Manufacturing AI Data CenterProposedImperial Valley Computer Manufacturing (IVCM) · Imperial, CA
3,400+ residents signed petition opposing project. Site is adjacent to two residential neighborhoods with hundreds of homes and within 1 mile of schools and playgrounds. City of Imperial filed 231-page court complaint citing noise, hazardous emissions, fire, explosion, and toxin risks. Residents organizing 'Imperial County Data Center Prohibition Act' for November 2026 ballot. Calipatria city council voted to draft a 5-year moratorium. Recall petition filed against County Chairwoman Peggy Price. Developer filed federal civil rights lawsuit against City of Imperial.
- Nebius Birmingham AI Factory (BHM01)Under constructionNebius Group · Birmingham, AL
Two lawsuits filed by Oxmoor Valley residents seeking injunctions; the first was dismissed May 29 2026, a second filed June 29 2026. Birmingham City Council approved a revised zoning ordinance June 9 2026 adding 20 data-center regulations, ending the moratorium debate over whether the January permit was validly grandfathered.
- Sentinel East Whiteland Data CenterPermittedSentinel Data Centers · East Whiteland Township, PA
Original 2018/2024 zoning and final-plan approvals are being challenged; a court called one challenge 'frivolous' (June 2026). An amended expansion plan seeks up to 1.6M sq ft / 100-600MW (a range, not a confirmed single figure).
- Sabey Decatur Technology ParkPermittedSabey Data Centers · Decatur Township, IN
Metro Development Commission approved via a 'variance of use' (bypassing full rezoning) in March 2026; 7 residents sued in Marion Superior Court for judicial review, developer filed a motion to dismiss June 2026, case pending.
- ColossusOperationalxAI · Memphis, TN
The NAACP (with SELC and Earthjustice) sued xAI over roughly 35 unpermitted methane gas turbines; the county permitted only 15, and the NAACP/SELC appeal to the Shelby County Air Pollution Control Board stays it. The permit drew 1,700+ public comments, most opposed, and South Memphis (Boxtown) residents already face elevated asthma and cancer rates. xAI did not pursue a Shelby County EDGE PILOT tax abatement; no public subsidy is on record.
- Fort SpunkyProposedPacifico Energy · TX
Approval revoked and now contested via developer lawsuit against Hood County.
- Google Project Louie (Morgan County)Under constructionGoogle · Monrovia, IN
Significant opposition. 'KEEP MONROVIA RURAL' signs appeared along roads and fields; multiple lawsuits filed challenging rezoning decisions, consolidated January 2026, ongoing as of mid-2026. Annexation dispute active July 2026: Monrovia sought to annex Google parcels; county transferred property to RDC under IC 36-4-3-4.3 to block; Google offered $12M sewer plant upgrade in exchange for dropping effort. County commissioners generally supportive (Commissioner Don Adams called Google 'good neighbors'). Google donated $200K to Monrovia FFA and $1M to local nonprofits.
- Google Project Skyway (Pine Island)ProposedGoogle · Pine Island, MN
- Markley Group One Lowell Data CenterOperationalMarkley Group · Lowell, MA
Massachusetts' first data center lawsuit filed April 27, 2026 in Middlesex County Superior Court by Honest Future for Lowell (10 plaintiffs) represented by Yale Law School Environmental Justice Clinic, Fitch Law Partners, and Conservation Law Foundation. Plaintiffs allege unlawful permitting; facility sits 84 feet from closest diesel engine to residential properties. Sacred Heart and Back Central neighborhoods are designated environmental justice communities. One-year moratorium on expansion passed by Lowell City Council.
- Project Delta Data Center – Stokes CountyProposedUndisclosed (rezoning applicant: Engineered Land Solutions) · Walnut Cove, NC
Lawsuit filed March 13, 2026 in Stokes County Superior Court by Southern Coalition for Social Justice and Southern Environmental Law Center, representing National Hairston Clan, CleanAIRE NC, Dan River Basin Association, 7 Directions of Service, and local residents. Rezoning challenged as lacking procedural safeguards required by NC law. Stokes County Board of Commissioners voted April 14, 2026 to void the January 12 rezoning and text amendment, acknowledging statutory notice failures. Developer ELS expressed intent to resubmit a compliant application; lawsuit remains pending.
- Project HazelnutProposedNorthPoint Development (NP Hazleton Holdings 1 LLC) · Hazle Township, PA
Hazle Township denied NorthPoint's land development application; NorthPoint is appealing in Luzerne County Court of Common Pleas and created a $30M fund to offset potential short-term utility rate increases for residents during the appeal. Separately, NorthPoint committed to a $165M Community Benefit Fund: $45M Direct Resident Grant Fund ($10,000 grants to eligible households), $15M Community Support Fund (education/workforce training/arts/recreation/youth), and a $105M long-term commitment ($7M/year for 15 years) toward a new local police department and reduced trash fees. A judge reportedly rebuked NorthPoint's appeal effort. Hazle Township subsequently passed a 6-month moratorium/curative amendment; PA state Sen. Katie Muth has filed a statewide 3-year data center moratorium bill.
- TenKey LandCo Project Lionsgate – Franklin Data CenterProposedTenKey LandCo I LLC · Franklin, KY
Two active lawsuits: (1) TenKey LandCo sues Simpson County in Simpson Circuit Court challenging a December 2025 county ordinance requiring conditional-use permits for data centers, arguing county lacks zoning authority inside Franklin city limits; (2) Franklin Citizens for Responsible Development sues the Franklin P&Z Commission alleging it lacked authority to approve the preliminary plan, which passed 3-2 in March 2026. Prior unanimous rejections by Franklin city council and planning commission. End user never publicly disclosed; developer refused to reveal it without NDAs.
Opposed · 14
- Brightseat Tech ParkPermittedLerner Enterprises / The Tower Companies (Brightseat Associates LLC) · Landover, MD
22,500+ petition signatures collected. County Executive Aisha Braveboy issued executive order in September 2025 pausing development. Separate county council moratorium on new applications. Qualified Data Center Task Force created. Predominantly Black community (63% African American census tract); environmental justice concerns raised.
- PowerHouse Data Centers – Louisville (Camp Ground Road)Under constructionPowerHouse Data Centers · Louisville, KY
Strong community opposition from Rubbertown-area residents citing energy affordability burdens on low-income customers, environmental and health equity concerns in a historically underserved West End neighborhood. Multiple public hearings with significant protests. Louisville Party for Socialism and Liberation among opponents.
- Nobles County Powered Data ParkProposedGeronimo Power (Brookfield Asset Management subsidiary) · Worthington, MN
Nobles County Board rejected the requested zoning change (~June 2026); no confirmation found of the developer abandoning or appealing the project, so status is recorded as proposed pending further news rather than presumed cancelled.
- TeraWulf AI Data Center Campus, LansingProposedTeraWulf / Cayuga Operating Company · Lansing, NY
19,700-signature petition (17,000 from NY state) submitted to Lansing Town Board. Tompkins County Legislature voted 12-1 on January 20, 2026 urging NYSDEC to reject water withdrawal permit. TeraWulf threatened legal action against Town of Lansing over alleged Open Meeting Law violations. Multiple adjacent towns (Dryden, Danby) passed laws blocking data center development in response.
- NE Edge Millstone Nuclear Data CenterCancelledNE Edge · Waterford, CT
Concerned Citizens of Waterford and East Lyme (CCWEL) formed in opposition. CT Siting Council denied Dominion's petition (January 2024) citing lack of information. Opposition demonstrated via ISO-NE data that both Millstone reactors were simultaneously inoperable for 5 weeks, contradicting developer's reliability claims. CT Attorney General reviewed monopolization concerns.
- Rowan Digital Infrastructure Frederick Campus (Bauxite I)Under constructionRowan Digital Infrastructure · MD
Neighboring residents raised health concerns over construction dust and traffic in November 2025. Frederick County overlay zone referendum effort collected 21,000+ signatures; Maryland Supreme Court case pending.
- Aligned Data Centers IAD-04 FrederickUnder constructionAligned Data Centers · MD
Frederick County Data Center Referendum Committee collected 21,000+ signatures opposing overlay zone expansion. Maryland Supreme Court scheduled to hear referendum appeal. Frederick County Council created Critical Digital Infrastructure Overlay Zone in January 2026.
- Cassville Data Center Campus (Undisclosed Developer)CancelledUndisclosed (major tech company, NDA not signed) · Cassville, WI
Residents voted 44-0 (April 16, 2026) to ban data centers in the township. 'No Data Centers in the Driftless' Facebook group reached 2,700 members. Community cited loss of farmland and rural character in Wisconsin's Driftless Area.
- Hanton City Business Park (data center anchor)ProposedHanton City Investments LLC · Smithfield, RI
Smithfield Town Council voted 4-1 (May 5, 2025) to amend zoning to list data centers as "not permitted" in all districts; Hanton City Investments filed its application May 4 — one day before the vote — preserving pre-ban review (a use variance faces "a pretty high bar"). Council President Tassoni expects the developer to sue. The widely cited $59M is projected 30-year town tax REVENUE, not facility investment; the developer said the project "may never happen" absent a state tax break (RI SB 2346, a 30-year sales/use exemption, was held by the Senate as of April 2026).
- La Osa Data Center ParkProposedVermaland LLC · Eloy, AZ
All approximately 60 public comments and 50 emails received by the Pinal County Board opposed the project. Concerns raised: location in a high-risk flood zone, wildlife and environmental impacts, water use risk, power bill impacts for local residents, construction timeline (gas plant likely last, 5-7 year timeline). Scale-back from 3 GW to 1 GW was a direct response to this opposition. Pinal County Supervisor Rich Vitiello expressed concern about constituent energy cost impacts.
- Meta Jeffersonville Data CenterUnder constructionMeta · Jeffersonville, IN
Community groups pushed back citing water supply burden (up to 5 million gallons/day estimated), energy cost impacts, and tax abatements while investment in local economy seen as insufficient. Wave3 News covered community opposition forum October 2025.
- Prince William Digital GatewayCancelledQTS / Compass Datacenters · Gainesville, VA
Extensive community opposition over proximity to Manassas National Battlefield and loss of rural character. State courts voided rezoning. County spent over $1.7M in taxpayer funds supporting developers before dropping appeal in April 2026.
- QTS Dane County Hyperscale Campus (DeForest)CancelledQTS Data Centers · DeForest, WI
The group 'No Data Center in DeForest' had 4,100+ members at withdrawal; the Village Board signaled a unanimous 7-0 denial of the annexation petition, citing transparency and watershed/land-use concerns. Opposition led directly to cancellation.
- Wiscasset Data Center (Old Ferry Road Site)ProposedUnnamed developer (NDA with town) · Wiscasset, ME
Grassroots group Protect Wiscasset formed by Richard Davis. Selectboard reportedly voted November 4, 2025 to pause data center discussions (primary source was published November 3, pre-vote). Lincoln County rescinded $240,000 in ARPA affordable housing funds from Wiscasset citing incompatibility between data center and housing on the same parcel. RePower Wiscasset also formed in opposition.
Contested · 58
- Stratos AI Data Center CampusProposedO'Leary Digital · Lucin, UT
Community opposition over fast-tracked MIDA process, CO2 emissions (~34M metric tons/year at full build), light/noise pollution, and Great Salt Lake impacts. Utah Senate President called for 75% footprint reduction; O'Leary agreed to cut acreage by 50% (remove ~20,000 acres). Governor Cox ordered 'careful consideration' of environmental impacts.
- Susquehanna Steam Electric StationOperationalTalen Energy · Berwick, PA
American Electric Power (AEP) and Exelon formally intervened at FERC against the co-located behind-the-meter ISA amendment, arguing it could shift up to $140 million/year in transmission costs onto PJM ratepayers as a 'free rider' benefit -- a factor in the ISA's rejection. This is a regulatory/ratepayer-cost dispute among utilities, not local community opposition; the front-of-meter restructuring addresses the underlying jurisdictional issue.
- Amazon Project RainierOperationalAmazon Web Services · New Carlisle, IN
IDEM cited Amazon and its contractor for unauthorized wetland impacts and halted work in affected areas pending Section 401 water-quality recertification; a April 2025 public hearing drew 100+ residents opposing a pending wetland-fill permit near Bendix Woods County Park, with concerns over aquifer depletion and utility rates. Amazon separately committed a ~$143M community enhancement agreement to St. Joseph County.
- Monarch Compute CampusProposedNscale · Point Pleasant, WV
60+ Mason County residents attended March 17, 2026 meeting to organize opposition; concerns over noise, light, water, and CO2 pollution. Marshall University and Mountwest Community College workforce training partnership established.
- AWS Project Galaxy — Sidney, OHUnder constructionAmazon Web Services · Sidney, OH
Active opposition from 'Sidney Citizens for Responsible Development' (founded by Kristin Allen, 4th-generation farm family) and 'Sidney Citizens Data Center Watch' (150+ Facebook members). Core concerns: per-job tax abatement economics ($2.4M–$4.6M in foregone tax revenue per permanent job), water capacity strain, and NDA limiting public transparency during approval process. Community town hall held March 6, 2026 with Shelby County Commissioners attending; no Sidney City Council members attended. City published FAQ in response to community pressure.
- Cloverleaf Project Open SkyProposedCloverleaf Infrastructure · Piedmont, OK
Piedmont Planning Commission recommended the City Council DENY the 'Project Open Sky' PUD rezoning pending additional information; Council vote rescheduled to late July 2026 — approval not yet granted as of this writing.
- Microsoft Fairwater Atlanta (Azure AI Superfactory)OperationalMicrosoft · Fayetteville, GA
Fayetteville adopted a 90-day moratorium (Jan 29 2026) then unanimously passed Ordinance 26-O-12 (March 5 2026) banning new data centers in all zoning districts; existing Fairwater 1/2 and the Dec 2025 East Campus rezoning are grandfathered. Opposition centered on construction traffic, the ~29M-gal unmetered water draw, and new 500 kV transmission lines; Mayor Edward Johnson expressed support. A competing Crow Holdings proposal withdrew its appeal after the ban. No litigation against the Fairwater campus.
- PAX — Pennsylvania Digital IUnder constructionPowerHouse Data Centers / Pennsylvania Data Center Partners · Carlisle, PA
Middlesex Township supervisors voted 3-0 (Ordinance 3-2025, May 30 2025) to create a 694-acre Data Center Overlay District making data centers a by-right use; Protect Cumberland County PA documents organized opposition over water, pollution, utility rates, and private-well impacts (Rep. Barb Gleim questioned utility-bill effects). No litigation as of 2026-07-08.
- Florida Ecopark AI Data Center CampusProposedStonebridge (via Florida Ecopark LLC; end tenant undisclosed) · Fort Meade, FL
Florida Commerce Secretary Alex Kelly called project 'fundamentally flawed' in April 17, 2026 letter citing water, energy, and transportation risks. Environmental advocates questioned water usage claims (reduced from 140,000 to 50,000 gallons/day) and generator emissions. Fort Meade Planning Commission recommended approval unanimously April 8, 2026. Fort Meade City Commission approved 20-year development agreement approximately April 15, 2026; 40 of 41 public commenters opposed at hearing. Southwest Florida Water Management District approval for water use permits remains outstanding — SWFWMD informed Fort Meade the city's current water permit cannot supply the data center and Stonebridge must apply separately.
- AVAIO Digital Leo CampusProposedAVAIO Digital Partners · AR
Pulaski County adopted a one-year data-center moratorium (10 votes) in May 2026 but exempted AVAIO by a bare 8-vote majority — the minimum on the 15-member Quorum Court. Residents opposed the project over water use and farmland; it is backed by state and county leadership and the Little Rock Regional Chamber.
- Google Nebraska AI Campus (proposed)ProposedGoogle · NE
Otoe County commissioners passed a one-year moratorium on new data-center permits (May 2026), with the board chair describing sentiment as '50/50'; the Gage County planning commission unanimously recommended an 18-month moratorium (June 2026) to applause. Opposition centers on water supply, power costs, land use, and limited permanent employment.
- Meta El Paso AI Data Center CampusUnder constructionMeta · El Paso, TX
Sembrando Esperanza Coalition and environmental groups oppose the proposed natural gas plant, citing air quality and rate equity concerns. Meta committed $500,000 to workforce development via El Paso Public Schools.
- Riot Platforms Corsicana FacilityOperationalRiot Platforms · Corsicana, TX
Organized local opposition (Concerned Citizens of Navarro County; Change.org petition). County commissioners declined an earlier, larger reinvestment-zone request in March 2024 after resident pushback; a smaller Chapter 312 abatement passed on a 3-2 vote in October 2024. Cited concerns: noise, peak water use, ERCOT grid strain, and limited permanent jobs relative to power draw.
- Stargate Project JupiterUnder constructionOpenAI / Oracle / STACK Infrastructure · Santa Teresa, NM
The NM Environmental Law Center sued the Doña Ana County Commission over the incentive approval; Sunland Park City Council asked for a postponement; the commission approved 4-1 amid audience opposition. Concerns center on water use in an arid region, air quality from the gas microgrids, and the speed and opacity of approvals. Investment is $50B over 5 years (up to $165B over 30 years).
- TeraWulf Morgantown Generating Station AI CampusProposedTeraWulf · MD
Charles County Planning Commission voted to recommend denial of ZTA in March 2026 and again in June 2026 public hearing (four hours of resident testimony). Charles County Against Data Centers Coalition active. County has no explicit data center zoning; commissioners voted 3-2 to send proposed ZTA back to planning board.
- Stargate Lighthouse CampusUnder constructionVantage Data Centers (for OpenAI / Oracle) · Port Washington, WI
An April 2026 referendum passed (~66%) requiring voter approval for future TIDs over $10M; Marquette polling found ~70% believe data-center costs outweigh benefits (the biggest sentiment shift in 14 years of polling); Great Lakes Neighbors United sued over the TID's legality. The existing TID 5 stands.
- Bitdeer Shalersville Data Center CampusProposedBitdeer (development partner: Geis Development) · Shalersville Township, OH
Standing-room-only town hall meetings; local opposition coverage from Kent Stater and The Portager. Shalersville Township has had a data-center moratorium in effect since October 2024, most recently extended through early November 2026 (signed April 7, 2026) to allow the township time to draft data-center-specific zoning regulations before any project can be permitted; trustees are separately considering making the moratorium permanent.
- Project BaccaraPermittedTakanock, LLC · AZ
Board of Supervisors approved 4-1 (May 2026).
- Project ShirleyProposedSentinel Data Centers · Eagle Creek Township, IN
Rezoning vote postponed to May 2026; Board of Zoning Appeals final permitting still required. Significant local opposition.
- Sioux Falls Technology Park (Gemini Data Center)PermittedGemini Data Center SD LLC · Sioux Falls, SD
The city council approved rezoning unanimously despite hours of opposing public testimony; a citizen petition drive is gathering signatures that could force the rezoning to a public vote. A state 50-year sales-tax exemption bill failed in the 2026 legislative session.
- Digital Realty Moores Chapel Data Center CampusPermittedDigital Realty · Charlotte, NC
Charlotte City Council approved the rezoning 7–4 in May 2025 over environmental and neighborhood objections (an earlier rezoning of the same parcel drew a ~1,300-signature petition), and metro-wide data-center pushback is intensifying — a comparable Matthews project was withdrawn in Oct 2025 after opposition. The site would likely qualify for North Carolina's statewide data-center sales-and-use tax exemption (which requires $75M+ investment), but no Secretary of Commerce determination for it is in the public record.
- NTT Global Data Centers Mesa — Pacific Proving Technology ParkProposedNTT Global Data Centers · Mesa, AZ
Residents packed June 2026 Mesa City Council meeting opposing rezoning, citing water use, heat, and drought. Planning Commission voted 4-0 to recommend approval; council vote was pending summer 2026.
- CoreWeave Lancaster Data CenterProposedCoreWeave · Lancaster, PA
Repurposing two former printing plants drew strong resident opposition (about 20 speakers against, none in favor, at one hearing) and a challenge to the zoning classification that bypassed public hearings; the city is drafting a data-center-specific ordinance. Notably, the developer is receiving no local tax breaks — the city confirmed LERTA and CRIZ do not apply — and instead signed a 20-year, ~$20M community benefits agreement, described as the first data-center-specific CBA in the US. Reported job figures conflict: the binding agreement cites ~2,000 construction and 350 permanent, while CoreWeave's own release cites ~600 construction and 70–175 permanent.
- Gainesville Crossing Digital Campus (GCDC)Under constructionCorscale Data Centers (Patrinely / USAA Real Estate) · Gainesville, VA
The Prince William County BOS approved the Gainesville Crossing rezoning (REZ2018-00008) 7-1 on Dec 10 2019 over opposition from the Coalition to Protect Prince William County (Elena Schlossberg: 'Citizens are carrying the burden of the massive infrastructure bills for these energy hogs'). Distinct from the separately-contested PW Digital Gateway / Pageland Lane project (voided by courts in 2025); GCDC's own approval is not under legal challenge.
- Google The Dalles Data Center CampusOperationalGoogle · The Dalles, OR
The city sued The Oregonian/OregonLive (with Google funding >$100K) to block release of Google's water data, then settled in December 2022 and released a decade of records. Concerns span water (Yakama Nation fishers and Dog River endangered-fish habitat), school funding, and abatement scale; Oregon enacted a 2025–26 pause on new data-center incentives.
- Riverview Innovation & Technology CampusProposedRiverview Innovation & Technology Campus · Tonawanda, NY
Hundreds of residents packed a June 3, 2026 Town of Tonawanda Planning Board meeting to oppose the project; concerns included cooling-system noise, comparisons to the Love Canal environmental disaster, and grid-strain concerns raised by Clean Air Coalition board chair Jim Jones. NY State Senator Jeremy Zellner (co-sponsor of a first-in-the-nation statewide data center moratorium bill) and Assemblyman Bill Conrad have both raised concerns publicly. Planning Board tabled further discussion pending a revised site plan application.
- CoreWeave NEST CampusUnder constructionCoreWeave · Kenilworth, NJ
The mayor backs the project as filling the economic gap left by Merck's departure, and CoreWeave is New Jersey-based. But residents circulated a petition with 1,500+ signatures citing water, flood-risk, and electricity-cost concerns, and the state froze the incentive program after broader backlash over power costs.
- Bitdeer Massillon FacilityUnder constructionBitdeer · Massillon, OH
Local opposition petition ("BitDeer Bitmine in Massillon" nuisance petition) circulated via MoveOn; a Massillon city council vote reportedly allowed the project to proceed, though the source for that vote could not be independently fetched/verified this session.
- CyrusOne AI Data Center at NAS LemooreProposedCyrusOne · CA
Kings County Supervisor Garrett Gilcrease (also Farm Bureau president) opposed the project on water grounds during his 2024 campaign; the project advanced with little public input; no formal legal challenge as of mid-2026. A 2023 EIR projects ~400 construction workers and ~20 permanent employees for the proposed facility (projections, not confirmed headcount). The ~$1B figure reported by the Hanford Sentinel covers the integrated project (data center + ~425 MW solar + battery storage), not the data center alone — so no data-center-only investmentUsd.
- Amazon AWS Gilroy Data CenterUnder constructionAmazon Web Services · Gilroy, CA
Organized resident opposition active. Concerns cited: utility cost spikes, noise, fire and explosion risk from large-scale lithium BESS, and objection to AI use. An appeal was filed July 21, 2025, subsequently withdrawn August 18, 2025. Opponents requested Amazon guarantee the facility would not be used exclusively for AI workloads.
- Microsoft Tyrone Campus (Project Rita)PermittedMicrosoft · Tyrone, GA
2024 rezoning drew limited opposition; by 2026 residents launched a Change.org petition seeking an independent environmental/infrastructure study and a moratorium on future data centers.
- DC BLOX Warren Township Data CenterProposedDC BLOX · Warren Township, IN
Opponents filed an appeal against the hearing examiner's June 11, 2026 approval recommendation; full City-County Council vote pending, likely August 2026.
- Crane PDX01Under constructionCrane Data Centers · Forest Grove, OR
Two-round appeal fight: planning staff approved (July 2024); a resident appeal was denied by the Planning Commission (4-2, Sept 3, 2024); a further appeal was denied by City Council (5-0, Oct 14, 2024). Opposition centered on building scale (~75 ft), shadowing of homes, wetlands/habitat, and grid strain. The project prevailed; no lawsuit found.
- Amazon Devlin Technology ParkPermittedAmazon Web Services · Bristow, VA
Bristow residents organized and challenged rezoning in court unsuccessfully. Site is adjacent to schools and homes. County is currently weighing whether to remove the data center overlay district entirely.
- Andover HPC Data Center (former Newton Airport Site)ProposedAndover HPC Development · Andover, NJ
Residents allege two ordinances (Sept 2025, April 2026) were illegally tailored to benefit a single developer. Legal challenge filed April 24, 2026 alleging violation of NJ Municipal Land Use Law. Andover Township voted in May 2026 to ban all data centers following intense community backlash. No formal site plan or application has been filed with the land use board.
- AWS Hobart CampusUnder constructionAmazon Web Services · Hobart, IN
Active opposition group 'No Data Centers Hobart Indiana'; majority of Plan Commission testimony opposed; concerns include noise, light, water/power use, property values; lawsuit filed in Lake County Court. Neighboring NWI communities have rejected similar projects.
- AWS Project Green CampusUnder constructionAmazon Web Services · New Florence, MO
Preserve Montgomery County LLC (coalition of local residents, farmers, and business owners) filed a 10-count lawsuit in February 2026 alleging Missouri Sunshine Law violations — specifically that county commissioners conducted negotiations in closed sessions and signed NDAs with Amazon. Community concerns at public meetings included water usage impacts, potential electric rate increases, and loss of rural character. Some residents and officials expressed support for the project's economic benefits. Construction proceeded despite the pending suit. Montgomery County Commission stated real property taxes are not abated and projected the project would double the county's tax revenue at full buildout.
- Comanche CircleProposedSailfish Digital Ventures (SDV) · Tolar, TX
Local opposition (Protect the Paluxy Valley group, aquifer/water concerns); a Feb 2026 county moratorium vote failed 3-2.
- Google Stillwater Data Center CampusPermittedGoogle · Stillwater, OK
All local taxing jurisdictions approved the 25-year incentive agreement, but Payne County Commissioner Rhonda Markum cast the lone dissenting vote, citing water and transparency concerns (officials were required to sign NDAs before learning project details). A Park View Estates homeowners association filed a civil suit in Payne County District Court against Google's Kipper LLC and its contractors over stormwater runoff/pollution from site grading.
- Homer City Energy CampusUnder constructionHomer City Redevelopment / Kiewit · Homer City, PA
A strong local-revival narrative (an economic anchor after the 2023 coal-plant closure, backed by state officials) meets organized environmental opposition — the air permit drew 500+ comments and Clean Air Council opposition citing ~17M tons CO2e/year, potentially Pennsylvania's largest single pollution source. Developers project ~10,000 construction and ~1,000 permanent jobs.
- Luckett Road Data Centers (Fremont Peak Properties)ProposedFremont Peak Properties LLC (Beale Infrastructure) · Marana, AZ
Marana Town Council approved rezoning 6-0 after hours of packed public testimony on water, power, and growth concerns. Opposition group Worker Power organized a referendum petition challenge; Marana officials rejected the referendum on a technicality (petition lacked required legal property descriptions), ending the challenge. Marana resident and cybersecurity expert Jackie McGuire raised concerns specifically about Blue Owl Capital (Beale Infrastructure's parent).
- Menomonie Data Center CampusProposedUndisclosed (Balloonist LLC) · Menomonie, WI
Active opposition group 'Stop the Menomonie Data Center'; Mayor Knaack (Sept 2025) called it 'not a suitable fit'; the city administrator signed an NDA limiting transparency; residents built a national toolkit for similar proposals; the new mayor is continuing the I-4 ordinance process.
- Meta Project Anthem — TulsaUnder constructionMeta · Tulsa, OK
Tulsa City Council passed a 9-month moratorium on new data centers in March 2026 to evaluate ecological impact; Project Anthem was carved out as it was approved before the moratorium vote. Approximately a dozen protesters from Stop Data Colonialism coalition gathered at the April 21, 2026 groundbreaking, raising concerns about environmental impact, financial burden on nearby residents, and 'data colonialism.' Meta's water-neutrality claims challenged by protesters as corporate narrative. Councilor Christian Bengel voted for the moratorium while separately supporting Project Anthem. Meta announced $3 million in community grants (Eastside Rise neighborhood enhancement, Data Center Community Action Grants) and workforce development partnerships with Tulsa Tech and Tulsa Community College targeting 200+ graduates annually in technical trades.
- Microsoft Kenosha Data Center CampusProposedMicrosoft · Kenosha, WI
Community concerns about noise, traffic, and community character reported in local coverage. Specific claim of 'dozens at November 2025 public meeting' cannot be verified from sources cited in this record; removed pending a sourced reference.
- PowerHouse Caldwell County Data CenterProposedPowerHouse Data Centers · Uhland, TX
Substantial pushback reported from residents at an open house.
- Project BoulderProposedEagle Rock Partners · SC
Facing zoning-appeals opposition and a county moratorium reconsideration.
- Project CannoliProposedGoogle (via Panattoni Development Co.) · Van Buren Township, MI
Planning commission gave preliminary approval (Feb 2026) for a substation/switching station; full Board of Trustees approval still pending. 1,900+ residents signed a petition opposing the project.
- Project FlexProposedVerrus (Sidewalk Infrastructure Partners) · Lyon Township, MI
Developer (via counsel) threatened injunctions/damages after the township denied a stormwater easement; a $10M community-benefits offer was floated July 2026.
- Project MatadorUnder constructionFermi America · Amarillo, TX
TCEQ air permit process (for 93 planned gas turbines) drew 279+ public comments, majority opposed. 63 contested case hearing requests filed before State Office of Administrative Hearings; 21 additional public meeting requests. Primary opposition group: Panhandle Taxpayers for Transparency. Key concerns: air quality (modeled 2,140 tpy CO and 1,591 tpy NOx), water demand, impacts on farmland and nearby cattle operations (Tyson Foods facility adjacent). Fermi bused in college students to a December 2025 public meeting, stoking further controversy.
- Project Spring (Sand Springs)ProposedGoogle · Sand Springs, OK
Protect Sand Springs Alliance filed an annexation-challenge lawsuit (Jan 2026); Land Legacy filed a conservation-easement enforcement suit (Mar 2026) covering 270 of the 827 acres; a recall petition targets the City Council and mayor; Osage Nation raised mineral-estate sovereignty and consultation concerns.
- Project Tango AI Data Center CampusProposedPBA Holdings (end tenant undisclosed) · Loxahatchee, FL
Over 8,000 Change.org petition signatures opposing project. Earthjustice filed letter requesting BCC deny application. February 2026 town hall drew hundreds of residents. Commissioners postponed vote 7-0 in December 2025 requiring additional impact studies. Developer scaled project back from 3.7M to ~1M sq ft after outcry. Final BCC vote scheduled July 15, 2026.
- QTS Bessemer (Project Marvel)ProposedQTS Data Centers (Blackstone) · Bessemer, AL
Strong and ongoing opposition. Public Facebook group 'Bessemer Data Center - We Say No!' grew to 720+ members. NAACP cited environmental justice concerns for majority-minority Bessemer community. Black Warrior Riverkeeper (BWR) and Southern Environmental Law Center (SELC) opposed construction over fossil fuel and water impacts. U.S. Fish and Wildlife Service raised concerns. Rezoning lawsuit filed in Jefferson County Circuit Court (temporarily enjoined; later dismissed). Bessemer City Council approved initial rezoning 5-2 in November 2025 despite crowd opposition (Councilman King and Councilwoman Thigpen dissented). 914-acre expansion rezoning approved April 2026. Some elected officials operated under NDAs with the developer prior to QTS confirmation. Homeowners filed additional lawsuits against the project.
- QTS Project EisenhowerUnder constructionQTS Data Centers (Blackstone) · Augusta, GA
Organized neighborhood opposition (Haynes Station / Captain's Corner) over transparency, noise, environmental impact, and Savannah River water use; residents spoke at Augusta Commission meetings (May-June 2026). Augusta approved a 49-day moratorium on NEW data centers (June 2026) that explicitly excludes this already-approved QTS campus. No lawsuit against this campus.
- Rural Hall Data Center (The Drox Group)ProposedThe Drox Group · Rural Hall, NC
Rezoning case F-1669, 129 acres across from Rural Hall Town Hall. Developer separately cited ~$80M in projected county tax revenue over 10 years.
- Social Circle Technology ParkProposedTPA Group (developer; end tenant undisclosed) · Social Circle, GA
Social Circle City Council unanimously approved a special-use permit for SC Infrastructure LLC (June 2025). A jurisdictional dispute exists — Newton County does not recognize the 2008 annexation of the site into Social Circle. Newton County enacted a 30-day moratorium on new data-center applications (April 2026); Social Circle and Covington enacted their own moratoriums. The project is "projected eventually to employ 200 people" (developer — a projection). No lawsuit against this specific project.
- Thor Equities Augusta Township Data Center (Form8tion)ProposedThor Equities · Augusta Township, MI
Protect Augusta Charter Township (PACT) organized referendum drive; 957 signatures collected (threshold 561). Residents cite water use (~1 million gallons/day), noise, light pollution, loss of rural farmland character. Board approved rezoning; voter referendum pending in 2026. No end user announced as of July 2026.
- Whitetail Creek Data CenterProposedBitdeer (via subsidiary Whitetail Creek LLC) · Niles / Weathersfield Township, OH
Niles City Council halted annexation talks April 20, 2026 after community backlash; no formal petition, zoning, or building-permit application was ever filed with the city. Weathersfield Township passed a 6-month moratorium.
- xAI SouthavenOperationalxAI · Southaven, MS
Safe and Sound Coalition (lifelong residents) cited lack of transparency; NAACP raised environmental concerns about pollution affecting Southaven and neighboring Memphis communities; residents allege public was not consulted prior to expansion.