Wisconsin
8 facilities tracked
8Sites
0 MWOperational
1.9 GWPlanned pipeline
1.9 GWUnder construction
§ By type
Facility type
Data center8 · 100%
§ By status
Lifecycle status
Under construction3 · 38%
Proposed3 · 38%
Cancelled2 · 25%
§ Community reception
Community reception
5Sites facing documented community friction
Contested, opposed, or in active litigation · out of 7 with a sourced community status.
§ Operators
Operators
- Microsoft2
- Meta1
- PCH WI Holdings LLC1
- QTS Data Centers1
- Undisclosed (Balloonist LLC)1
- Undisclosed (major tech company, NDA not signed)1
- Vantage Data Centers (for OpenAI / Oracle)1
§ Facilities
Facilities in Wisconsin
- Microsoft Mount Pleasant Data Center CampusMicrosoft · Mount Pleasant, WIUnder construction1,000 MW planned
- Stargate Lighthouse CampusVantage Data Centers (for OpenAI / Oracle) · Port Washington, WIUnder construction902 MW planned
- Cassville Data Center Campus (Undisclosed Developer)Undisclosed (major tech company, NDA not signed) · Cassville, WICancelled—
- Menomonie Data Center CampusUndisclosed (Balloonist LLC) · Menomonie, WIProposed—
- Meta Beaver Dam Data Center CampusMeta · Beaver Dam, WIUnder construction—
- Microsoft Kenosha Data Center CampusMicrosoft · Kenosha, WIProposed—
- QTS Dane County Hyperscale Campus (DeForest)QTS Data Centers · DeForest, WICancelled—
- Wisconsin Rapids Data CenterPCH WI Holdings LLC · Wisconsin Rapids, WIProposed—