Oak Harbor, OH · Ottawa County · 41.597°N 83.086°W
Straight-line distances. Nearest named waterway via the USGS National Hydrography Dataset; nearest transmission line via HIFLD. Baseline water stress and groundwater trend describe the surrounding hydrological basin (WRI Aqueduct 4.0, CC BY 4.0) — not this facility’s measured water use. Principal-aquifer system underlying the location (USGS, mapped at 1:2,500,000 — regional context, not site hydrogeology).
Supplies power to MetaCompany-level / grid-region purchase — no single named campus.
Part of the Jan 2026 Vistra-Meta 20-year PPA package (2,609 MW across three Vistra nuclear plants). Meta takes 100% of Davis-Besse's 908 MW operating output plus an 80 MW share of a fleet-wide uprate program. Grid-matched — power continues to the PJM grid (Vistra cites serving Meta's Ohio load, including its New Albany 'Prometheus' cluster), not a single dedicated campus, so no poweredFacilityIds. Operated by Vistra since the 2024 Energy Harbor acquisition; license to 2037.
Single-unit ~908 MWe net PWR (commercial operation 1978), delivering into the PJM grid. Meta contracts 908 MW of existing output plus an 80 MW uprate share under a 20-year PPA.
Vistra and Meta announced a 20-year PPA; Meta contracts the plant's full 908 MW existing output plus an 80 MW share of a planned uprate (988 MW total), per Vistra's SEC Form 8-K.
Vistra and Meta Announce Agreements to Support Nuclear Plants in PJMConfirmed: data verified against official filings, permits, or direct operator announcements.
Last updated:
Compute Atlas is meant to be corrected. If you have better, source-backed data on this facility, suggest a change — it’s reviewed before anything updates.