NV · Storey County · 39.531°N 119.492°W
Filed as the 'Peru Ridge Self-Generation Project'; together with the 144 MW South Valley project it accounts for about 362 MW of proposed temporary on-site generation at the Tahoe Reno Industrial Center, intended to run two to three years until NV Energy can serve the campuses.
Behind-the-meter temporary generation using natural gas and diesel engines requiring round-the-clock deliveries of liquefied or compressed natural gas.
Environmental advocates, including the Sierra Club Toiyabe Chapter, objected that behind-the-meter generation reduces public regulatory oversight.
Why a Northern Nevada data center wants to build its own temporary natural gas power plantApplication filed with Nevada state energy regulators; air-quality permit application submitted to the Nevada Division of Environmental Protection.
Why a Northern Nevada data center wants to build its own temporary natural gas power plantReported: data based on credible news outlets or industry sources.