NV · Storey County · 39.510°N 119.456°W
Reported as roughly 90 natural gas fueled engines with about 40 LNG holding tanks, intended to run for two to three years until NV Energy can provide permanent service to the South Valley data center campus at the Tahoe Reno Industrial Center.
Behind-the-meter temporary generation using natural gas fueled reciprocating engines, supplied by round-the-clock deliveries of liquefied/compressed natural gas held in on-site tanks.
The Sierra Club Toiyabe Chapter criticized behind-the-meter generation as locking the public out of the regulatory process; county officials described it as a new development for industrial power generation at TRIC.
Why a Northern Nevada data center wants to build its own temporary natural gas power plantApplication filed with Nevada state energy regulators for temporary self-generation; air-quality permit application also submitted to the Nevada Division of Environmental Protection.
Why a Northern Nevada data center wants to build its own temporary natural gas power plantReported: data based on credible news outlets or industry sources.