West Jordan, UT · Salt Lake County · 40.574°N 112.046°W
Straight-line distances. Nearest named waterway via the USGS National Hydrography Dataset; nearest transmission line via HIFLD. Baseline water stress and groundwater trend describe the surrounding hydrological basin (WRI Aqueduct 4.0, CC BY 4.0) — not this facility’s measured water use. Principal-aquifer system underlying the location (USGS, mapped at 1:2,500,000 — regional context, not site hydrogeology).
Novva's own facility page describes a centralized 200MW on-campus substation with N+1 redundancy serving the four-phase campus, plus a planned 15MW-30MW of on-site solar. The 175MW figure is the campus's stated total data center capacity at four-phase completion; the 200MW is substation capacity, not IT load.
Novva states the campus uses waterless air-cooled chillers with no evaporative water loss, citing a 1.18 annualized PUE and roughly 394,667 gallons per month (about 4.7 million gallons annually) of total site water use, which it compares to the consumption of 26 homes. Vendor-stated figures, not independently metered.
No recorded status history yet.
Confirmed: data verified against official filings, permits, or direct operator announcements.
Last updated:
Compute Atlas is meant to be corrected. If you have better, source-backed data on this facility, suggest a change — it’s reviewed before anything updates.