Nesquehoning, PA · Carbon County · 40.856°N 75.828°W
Bitfarms Ltd. (Keel Infrastructure Corp.)
Straight-line distances. Nearest named waterway via the USGS National Hydrography Dataset; nearest transmission line via HIFLD. Baseline water stress and groundwater trend describe the surrounding hydrological basin (WRI Aqueduct 4.0, CC BY 4.0) — not this facility’s measured water use. Principal-aquifer system underlying the location (USGS, mapped at 1:2,500,000 — regional context, not site hydrogeology).
Coal-refuse (culm) waste-to-energy generation; PJM wholesale market; PPL Electric Utilities interconnection for the planned HPC/AI load.
Bitfarms Ltd. (now Keel Infrastructure Corp.) completes its merger with Stronghold Digital Mining, Inc., assuming ownership of the Panther Creek coal-refuse power plant, which co-locates Bitcoin mining with its own power generation.
Keel Infrastructure Corp. (fka Bitfarms Ltd.) FY2025 Form 10-K, filed 2026-03-31Per the company's Q1 2026 results, the disclosed 350 MW HPC/AI data-center conversion (via a PPL Electric Utilities Electric Service Agreement) remains pre-construction: zoning secured, site development progressing toward lease signing; no groundbreaking or Notice to Proceed confirmed in any filing through this date.
Keel Infrastructure Corp. Q1 2026 results press release (May 11, 2026)Confirmed: data verified against official filings, permits, or direct operator announcements.
Last updated:
Compute Atlas is meant to be corrected. If you have better, source-backed data on this facility, suggest a change — it’s reviewed before anything updates.